Site planning
When mesh-mounted slips save time
The often-quoted 40% installation saving is a planning target. A timed trial on the actual substrate tells you what to allow in the tender.

Choose the right wall for the trial
Use a representative bay with its real openings and returns. Compare loose and mesh sections with the same bond, mortar, access and crew. Record setup, setting out, cutting, laying, pointing and clean-up separately.
Measure the complete operation
A 10-hour loose laying operation that takes 6 hours on mesh saves 40% of laying time. If pointing and preparation take another 5 hours for both methods, total labour falls from 15 to 11 hours. Put that distinction in the estimate.
Break the sheet repeat
Dry-lay adjacent sheets to check pitch and stagger. Blend cartons and use loose infill at sheet boundaries, jambs and corners. Check the mesh backing and adhesive combination against the service environment.
Carry the result into procurement
Record installed area per crew-hour and the number of cuts per bay. Recheck the advantage on small piers or heavily interrupted walls. Ask for sheets, infill flats and corner returns as separate lines on the packing list.